Projects
/

Urban construction and engineering supply

Design of fresh and waste water network for temporary buildings to be built according to the partial general plan of the first phase of the "Auto Trade Complex"

Design of fresh and waste water network for temporary buildings to be built according to the partial general plan of the first phase of the "Auto Trade Complex"

Customer:

"Auto Trade Complex"

Location:

Ulaanbaatar, Songinokhairkhan district

Implmented date:

2014

Project create

Designing of a 6.4 km water supply line with a diameter of 200-300 mm and a 6.6 km sewage line with a diameter of 200 mm for the service center of the auto trade complex was developed.

Project details